How long would it take your backup supplier to deliver?
Picture a small manufacturer in Scotland. It has eight working days’ worth of a component that goes into every unit it ships. On Monday, the supplier calls to say its machine is down. The buyer rings the firm listed as a backup and learns that its first available production slot is three weeks away.
The buyer has a second phone number. The factory still has a gap to cover. A useful backup is one that can deliver enough of the right part before the line stops. You can find out whether it can do that while your regular supplier is still delivering.

Start with the part that stops the line
Walk through next week’s production schedule with whoever runs the floor. Ask what they would have to stop making if a delivery failed to turn up. A seal that costs pennies might hold up more orders than a costly part that goes into a product you make once a month.
Count stock you can actually use. Some may be reserved for another job or waiting for inspection. If you have 640 usable seals and go through 80 each working day, you have eight days of cover at that rate. Put the date you expect to run out alongside the earliest date the backup can deliver. Include time to check the goods when they arrive. If the dates leave a gap, you’ll need to cover it, perhaps by bringing forward a different job or keeping more of that part in stock.
Find out what the two suppliers share
Two suppliers may buy the same material from the same mill. They might send work to the same coating shop, too. If the coating shop goes down, an order placed with either supplier can end up waiting in the same queue.
Start with the operation that is hardest to move. Ask each supplier where it is done and whether an alternative can meet your requirements. There may be a good reason to use the same specialist. It helps to know that before you count the second supplier as cover. Caventis’s guide to supply chain resilience explains how to map dependencies at supplier and site level and decide where a second source makes sense.
Ask what they can ship in the first week
A plant may have capacity for your usual monthly order once it has had time to plan. What matters during a stoppage is when it could make the first batch and how much of it you would get. Ask for a delivery date and quantity based on its current schedule and material stocks. A small batch that keeps one line going can buy time, even if it won’t cover all your orders.
If your own tooling would have to move, check who can release it and how long that will take. Ask the backup to run a small order before you depend on it. This lets your team test the handover from placing the order through to booking the parts into stock. If the shortlist is thin, Caventis’s product sourcing service sets out how it finds and qualifies alternatives for UK buyers.
The backup may need occasional orders to hold a slot or keep material on hand. Find out what it expects from you and what it can commit to in return. Agree on the first batch it could deliver at short notice and revisit that promise when either business changes its production schedule.
Write down who can authorise the switch and when they should make the call. If the backup needs six working days and you have eight days’ stock, you have two days to make the decision, assuming usage stays steady and the six days include checks at your end. If an engineer tells you on Monday that the repair date is uncertain, waiting until Friday to place the order leaves a gap you could have avoided.